24 Arbeiter können einen Bauauftrag in 8 Tagen ausführen. Nach zwei Arbeitstagen werden 8 Arbeiter abgezogen. a) Wie lange brauchen die verbliebenen Arbeiter, um die Arbeit zu beenden?
b) Um wie viele Tage verzögert sich der Bauauftrag?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 13:30
At dinner, 2/5 of the people had fish and 1/3 had chicken. if everyone else had lamb, what fraction of the people had lamb? and if 40 people had lamb , calculate the total number of people at the dinner.
Answers: 1
question
Mathematics, 21.06.2019 16:20
Which equation matches the graph shown ?
Answers: 2
question
Mathematics, 21.06.2019 19:30
Weekly wages at a certain factory are normally distributed with a mean of $400 and a standard deviation of $50. find the probability that a worker selected at random makes between $450 and $500
Answers: 2
question
Mathematics, 21.06.2019 20:10
Which is f(5) for the function –2x2 + 2x - 3?
Answers: 1
You know the right answer?
24 Arbeiter können einen Bauauftrag in 8 Tagen ausführen. Nach zwei Arbeitstagen werden 8 Arbeiter a...
Questions
question
Mathematics, 06.04.2021 20:30
question
Mathematics, 06.04.2021 20:30
Questions on the website: 13722361