A and B, working together can finish a piece of work in 6 days, while A alone can do it in 9 days. How much time will B alone take to finish it?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 15:00
Consider the diagram. which line segment has the same measure as st? rx tx sr xs
Answers: 3
question
Mathematics, 21.06.2019 16:30
Abby is preparing fruit punch for her party. she starts with a bowl filled with liquid that has 1/2 fruit juice and 1/2 sprite, but she decides it's too fruity. so she pours out 1/4 of the liquid, and then fills the bowl up again with sprite. what fraction of the punch is now sprite?
Answers: 1
question
Mathematics, 21.06.2019 17:00
Me! last question, and i'm stuck! write the algebraic expression that models the word phrase. the product of 2 divided by the number h and 8 more than the number k
Answers: 1
question
Mathematics, 21.06.2019 18:00
Simplify the expression. -2/5(10+15m-20n)
Answers: 1
You know the right answer?
A and B, working together can finish a piece of work in 6 days, while A alone can do it in 9 days. H...
Questions
question
Mathematics, 25.03.2021 21:20
question
Mathematics, 25.03.2021 21:20
question
Mathematics, 25.03.2021 21:20
question
Mathematics, 25.03.2021 21:20
question
Mathematics, 25.03.2021 21:20
question
Biology, 25.03.2021 21:20
Questions on the website: 13722359