subject
Mathematics, 29.01.2021 22:50 LilyFlower227

4) The overall project budget is $20,000. At Week 8, the actual cost is $9,000 and the CPI is 1.1. What is the earned value of the project at Week 8?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:10
The number of hours per week that the television is turned on is determined for each family in a sample. the mean of the data is 37 hours and the median is 33.2 hours. twenty-four of the families in the sample turned on the television for 22 hours or less for the week. the 13th percentile of the data is 22 hours. approximately how many families are in the sample? round your answer to the nearest integer.
Answers: 1
question
Mathematics, 21.06.2019 17:00
16. you're planning to buy a boat, a motor, and some miscellaneous boating equipment. the boat costs $325, the motor costs $225, and the equipment costs $79. if you've saved $438 toward these purchases, how much more do you need to save? a. $181 b. $281 c. $291 d. $191
Answers: 3
question
Mathematics, 21.06.2019 17:30
Which of the following is true for the relation f(x)=2x^2+1
Answers: 1
question
Mathematics, 21.06.2019 19:30
For what values of the variable x is the expression square root of 7x+14+ square root of 7-x a real number?
Answers: 1
You know the right answer?
4) The overall project budget is $20,000. At Week 8, the actual cost is $9,000 and the CPI is 1.1....
Questions
question
Mathematics, 12.04.2020 06:04
question
Mathematics, 12.04.2020 06:05
question
Mathematics, 12.04.2020 06:06
question
Mathematics, 12.04.2020 06:06
question
Mathematics, 12.04.2020 06:06
Questions on the website: 13722362