12 obreros se demoran 3 días para realizar un trabajo, cuántos días se demorarán si se tienen la mitad de 8 obreros

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
1foot = 12 inches; 1 yard = 3 feet
Answers: 3
question
Mathematics, 21.06.2019 18:00
What does the relationship between the mean and median reveal about the shape of the data
Answers: 1
question
Mathematics, 21.06.2019 19:00
The graph shows the charges for a health club in a month. make a function table for the input-output values. writes an equation that can be used to find the total charge y for the number of x classes
Answers: 2
question
Mathematics, 21.06.2019 20:00
Elizabeth is using a sample to study american alligators. she plots the lengths of their tails against their total lengths to find the relationship between the two attributes. which point is an outlier in this data set?
Answers: 1
You know the right answer?
12 obreros se demoran 3 días para realizar un trabajo, cuántos días se demorarán si se tienen la mit...
Questions
question
Computers and Technology, 28.07.2019 12:00
Questions on the website: 13722361