Mathematics, 31.01.2021 16:00 privise
15 men can finish a piece of work in 40 days. How many more men should be added so that the work will be finished in 30 days?
Answers: 1
Mathematics, 21.06.2019 18:20
Inez has a phone card. the graph shows the number of minutes that remain on her phone card a certain number of days.
Answers: 2
Mathematics, 21.06.2019 20:00
Guys i need ! graded assignment grade 8 checkpoint 2, part 2 answer the questions below. when you are finished, submit this assignment to your teacher by the due date for full credit. total score: of 9 points (score for question 1: of 4 points) 1. the cost of renting a car for a day is $0.50 per mile plus a $15 flat fee. (a) write an equation to represent this relationship. let x be the number of miles driven and y be the total cost for the day. (b) what does the graph of this equation form on a coordinate plane? explain. (c) what is the slope and the y-intercept of the graph of the relationship? explain.
Answers: 1
Mathematics, 21.06.2019 20:30
The areas of two similar triangles are 72dm2 and 50dm2. the sum of their perimeters is 226dm. what is the perimeter of each of these triangles?
Answers: 1
Mathematics, 21.06.2019 20:40
Which questions would most a reader identify the author's purpose for writing? check all that apply. what type of text is this? what type of reviews did the book receive? how many copies of the book have been sold? what is the central idea? how does this text make one feel?
Answers: 2
15 men can finish a piece of work in 40 days. How many more men should be added so that the work wil...
Chemistry, 15.11.2019 05:31
Health, 15.11.2019 05:31
English, 15.11.2019 05:31
Computers and Technology, 15.11.2019 05:31
English, 15.11.2019 05:31
History, 15.11.2019 05:31
World Languages, 15.11.2019 05:31
Mathematics, 15.11.2019 05:31
Mathematics, 15.11.2019 05:31
Mathematics, 15.11.2019 05:31
Chemistry, 15.11.2019 05:31
Computers and Technology, 15.11.2019 05:31