The number of days, D. to complete research is inversely proportional to the number of researchers, who are working
The research takes 125 days to complete when 24 people work on it.
Find out how many people are needed to complete the research in 60 days.

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 16:30
The solution set for 5v2 – 125 = 0 is
Answers: 1
question
Mathematics, 21.06.2019 16:50
The parabola opens: y=√x-4 (principal square root) up down right left
Answers: 1
question
Mathematics, 21.06.2019 18:00
Aplane is taking off from bangladesh headed to new york city. at the same time, a plane from new york city is headed to bangladesh is also taking off. the plane bound to new york city is traveling at 600 mph, while the plane traveling to bangladesh is traveling at 400 mph. how far from new york city will the two planes meet if the distance between new york city and bangladesh is 8,000 miles?
Answers: 3
question
Mathematics, 21.06.2019 20:00
Aquadratic equation in standard from is written ax^2= bx+c, where a,b and c are real numbers and a is not zero?
Answers: 1
You know the right answer?
The number of days, D. to complete research is inversely proportional to the number of researchers,...
Questions
question
English, 04.01.2020 09:31
question
English, 04.01.2020 09:31
Questions on the website: 13722361