Mathematics, 10.02.2021 01:00 pandaniezzy

URGENT The time required to complete a job varies inversely as the number of people working. It took 4 hours for 7 electricians to wire a building. How long would it have taken 3 electricians?

A. 1 hour 43 minutes
B. 5 hours 15 minutes
C. 7 hours 30 minutes
D. 9 hours and 20 minutes

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 18:00
Which statement about the relative areas of δabc and δxyz is true? the area of δabc > the area of δxyz the area of δabc < the area of δxyz the area of δabc = the area of δxyz more information is needed to compare.
Answers: 1
question
Mathematics, 21.06.2019 22:30
If a flying disk is 139 meters in the air and travels at an average of 13 m/s how long is it in the air
Answers: 2
question
Mathematics, 22.06.2019 00:00
Abowl contained 270 starbursts of all different colors. if the probability of picking a yellow is 1/9, then how many yellow starbursts are in the bowl ? ?
Answers: 1
question
Mathematics, 22.06.2019 00:20
Astudent showed the steps below while solving the inequality |x-4|< 1 by graphing.
Answers: 3
You know the right answer?
URGENT The time required to complete a job varies inversely as the number of people working. It too...
Questions
question
History, 15.09.2021 03:40
question
Mathematics, 15.09.2021 03:40
question
Mathematics, 15.09.2021 03:50
question
Mathematics, 15.09.2021 03:50
question
Mathematics, 15.09.2021 03:50
question
English, 15.09.2021 03:50
question
Mathematics, 15.09.2021 03:50
question
Mathematics, 15.09.2021 03:50
Questions on the website: 13722359