Mathematics, 11.02.2021 14:00 nickeh30

The number of days, d, to build a house is given by 780
d =
W
where w is the number of workers used each day on site.
Bob's company will take 60 days to build the house.
Pat's company will take 39 days to build the house.
Pat's company will have to use more workers each day than Bob's company.
How many more?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 13:10
What graph correctly matches the equation y equals two negative x
Answers: 1
question
Mathematics, 21.06.2019 19:00
What is the best way to answer questions with a x expression in the question. for example 3x + 10x=?
Answers: 1
question
Mathematics, 21.06.2019 20:50
Amanda went into the grocery business starting with five stores. after one year, she opened two more stores. after two years, she opened two more stores than the previous year. if amanda expands her grocery business following the same pattern, which of the following graphs represents the number of stores she will own over time?
Answers: 3
question
Mathematics, 21.06.2019 22:30
How can constraints be used to model a real-world situation?
Answers: 1
You know the right answer?
The number of days, d, to build a house is given by 780
d =
W
where w is the numb...
Questions
question
Mathematics, 08.03.2021 05:20
question
Mathematics, 08.03.2021 05:20
question
Mathematics, 08.03.2021 05:20
question
Mathematics, 08.03.2021 05:20
Questions on the website: 13722363