The number of days, d, to build a house is given by
780
d =
W
where w is the number of workers used each day on site.
Bob's company will take 60 days to build the house.
Pat's company will take 39 days to build the house.
Pat's company will have to use more workers each day than Bob's company.
How many more?
Answers: 3
Mathematics, 21.06.2019 19:00
Jack did 3/5 of all problems on his weekend homework before sunday. on sunday he solved 1/3 of what was left and the last 4 problems. how many problems were assigned for the weekend?
Answers: 1
Mathematics, 21.06.2019 21:00
Simplify. 4+3/7x-2-2/7x a. 2-5/7x b. 6-1/7x c. 2+1/7x d. 6+5/7x
Answers: 1
Mathematics, 21.06.2019 21:00
Given: circle o, cd is diameter, chord ab || cd. arc ab = 74°, find arc ca.
Answers: 1
Mathematics, 21.06.2019 22:30
What is the distance from zero if a quadratic function has a line of symmetry at x=-3 and a zero at 4
Answers: 1
Business, 13.11.2020 14:00
Mathematics, 13.11.2020 14:00
Mathematics, 13.11.2020 14:00
Physics, 13.11.2020 14:00
Mathematics, 13.11.2020 14:00
English, 13.11.2020 14:00
English, 13.11.2020 14:00
Physics, 13.11.2020 14:00
Mathematics, 13.11.2020 14:00
Physics, 13.11.2020 14:00
Spanish, 13.11.2020 14:00
History, 13.11.2020 14:00