Activity Immediate Predecessor Optimistic Most Likely Pessimistic Sigma Variance A - 2 3 4 0.333 0.111 B - 2 5 8 1 1 C A 1 2 9 1.33 1.78 D A 5 5 5 0 0 E B, C 6 7 8 0.333 0.111 F B 14 14 14 0 0 G D, E 1 5 9 1.333 1.78 H G, F 1 4 8 1.67 1.362 If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer, what mean and standard deviation would be used

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:20
An equation representing lyleโ€™s hedge-trimming business is a = 12n - 300 where a is the amount of profit or loss in dollars and n is the number of hedges trimmed. how would the graph of lyleโ€™s business change if the equation a = 10n - 300 represented his business? the graph would be flatter. the graph would be steeper. the graph would start closer to the origin. the graph would start lower on the y-axis.
Answers: 2
question
Mathematics, 21.06.2019 16:30
How to choose the sign of the radical in the denominator of the formula for the distance from a point to a line.
Answers: 2
question
Mathematics, 21.06.2019 20:00
Combine like terms to make a simpler expression 3z+z
Answers: 2
question
Mathematics, 21.06.2019 21:00
Jordan got 27 out of 90 correct on his test . what fraction of the marks did her get correct
Answers: 2
You know the right answer?
Activity Immediate Predecessor Optimistic Most Likely Pessimistic Sigma Variance A - 2 3 4 0.333 0.1...
Questions
question
Mathematics, 19.01.2021 14:00
question
Mathematics, 19.01.2021 14:00
question
Computers and Technology, 19.01.2021 14:00
question
Mathematics, 19.01.2021 14:00
question
Business, 19.01.2021 14:00
question
Mathematics, 19.01.2021 14:00
question
Mathematics, 19.01.2021 14:00
question
Mathematics, 19.01.2021 14:00
Questions on the website: 13722360