subject
Mathematics, 18.02.2021 21:10 lashondrascott

Acme Widgets had an order to process 250 widgets. The first unit required 200 minutes to assemble. Before starting, the company estimated the amount of time it would require to assemble all 250 widgets if they learned at an 85% rate. After assembling all 250 widgets, Acme realized they had learned at an 80% rate. How much time less than their estimate did Acme take

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 21:00
Can some one explain how to slove specifically, what is the value of x? 0.9(x+1.4)-2.3+0.1x=1.6 enter the answer as a decimal in the box. x= ?
Answers: 2
question
Mathematics, 21.06.2019 22:00
The birth weights of newborn babies in the unites states follow in a normal distrubution with a mean of 3.4 kg and standard deviation of 0.6 kg. reaserches interested in studying how. children gain weights decide to take random samples of 100 newborn babies and calculate the sample mean birth weights for each sample
Answers: 1
question
Mathematics, 22.06.2019 00:00
The volume of the a sphere whoes diameter is 18 cm is cubic cm . if it's diameter were reduced by half, it's volume would be of its original volume
Answers: 1
question
Mathematics, 22.06.2019 00:00
Arectangle plot measure 20ft. by 30ft. a 3-ft.-wide sidewalk surrounds it.find the area of the sidewalk.
Answers: 1
You know the right answer?
Acme Widgets had an order to process 250 widgets. The first unit required 200 minutes to assemble. B...
Questions
question
Mathematics, 19.03.2021 19:20
question
Mathematics, 19.03.2021 19:20
question
Mathematics, 19.03.2021 19:20
question
Mathematics, 19.03.2021 19:20
question
Mathematics, 19.03.2021 19:20
Questions on the website: 13722361