Eight bricklayers on a building site took 25 hours to build a wall. The Site Manager needs a similar wall built.

He can hire five bricklayers to build this wall.

He needs to know how much longer it will take to build this wall.

How much longer will it take?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 13:30
If jm equals 5x -8 and lm equals 2x -6 which expression represents jl
Answers: 1
question
Mathematics, 21.06.2019 16:00
Arectangle with an area of 47 mΒ² is dilated by a factor of 7. what is the area of the dilated rectangle? enter your answer in the box. do not leave your answer as a fraction.
Answers: 1
question
Mathematics, 21.06.2019 22:40
Aclassmate thinks that solving a system by graphing gives an exact answer when the lines appear to cross at a grid point, but only an approximate answer when they don't. explain why this isn't true.
Answers: 3
question
Mathematics, 22.06.2019 00:20
Aline is perpendicular to another line m2= (-1/m1), where m1 is the slope of the original line and m2 is the slope of the perpendicular line. which of the following equations represents the line that passes through the point (-2,1) and is perpendicular to the line below?
Answers: 2
You know the right answer?
Eight bricklayers on a building site took 25 hours to build a wall. The Site Manager needs a simila...
Questions
question
Social Studies, 24.06.2019 15:10
question
Social Studies, 24.06.2019 15:10
question
Mathematics, 24.06.2019 15:10
Questions on the website: 13722363