Mathematics, 22.10.2019 21:10 raylynnreece5052

28 men can finish the job in 60 days. at the start of the 16 day, 5 men were laid off and after the 45th, 10 more men were hired. how many days were delayed in finishing the job? explain, step by step.

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:30
Part of the total score for each program is the sum of five program component scores. on the free program, the sum of these five program component scores is multiplied by a factor of 2.0. yuzuru hanyu, of japan, earned scores of 9.07, 8.96, 8.89, 9.21, and 9.36 for the program components portion of his free program. how many total points did he receive for this portion?
Answers: 1
question
Mathematics, 21.06.2019 16:20
Which equation matches the graph shown ?
Answers: 2
question
Mathematics, 21.06.2019 18:00
Plz a. s. a. p.the table shows the number of male and female contestants who did not win a prize. what is the probability that a randomly selected contestant won a prize, given that the contestant was female? write the probability as a percent. round to the neares tenth, if needed.
Answers: 1
question
Mathematics, 21.06.2019 18:30
Which value would be a solution for x in the inequality 47-4x< 7
Answers: 1
You know the right answer?
28 men can finish the job in 60 days. at the start of the 16 day, 5 men were laid off and after the...
Questions
question
Mathematics, 14.01.2021 07:20
question
Mathematics, 14.01.2021 07:20
question
Mathematics, 14.01.2021 07:20
Questions on the website: 13722363