A construction company has to complete a project no later than 3 months from now or there will be significant cost overruns. The manager of the construction company believes that there are four possible values for the random variable X, the number of months from now it will take to complete this project: 2, 2.5, 3, 3.5. The manager currently thinks that the probabilities of these four possibilities are in the ratio 1 to 2 and 2 to 4. That is X = 2.5 is twice as likely as X = 2, and X = 3 is twice as likely as X = 2.5 and X = 3.5 is half as likely as X = 3.
1) Find the probability distribution of X. Hint: P(X = 2) = 0.111, P(X = 3) = 0.444
2) What is the probability that this project will not be completed on time?
3) What is the expected completion time in months?
4) How much variability (in months) exists around the expected value?
Answers: 3
Mathematics, 21.06.2019 19:00
How is working backward similar to solving an equation?
Answers: 1
Mathematics, 21.06.2019 20:50
A. what is the area of the base? use complete sentences to explain your reasoning. b. what is the volume of the prism? use complete sentences to explain your reasoning.
Answers: 1
Mathematics, 21.06.2019 23:40
Determine the standard form of the equation of the line that passes through (-2,0) and (8,-5)
Answers: 1
A construction company has to complete a project no later than 3 months from now or there will be si...
Mathematics, 03.07.2019 10:00
Social Studies, 03.07.2019 10:00
Mathematics, 03.07.2019 10:00
Health, 03.07.2019 10:00
Mathematics, 03.07.2019 10:00
Physics, 03.07.2019 10:00
Mathematics, 03.07.2019 10:00
English, 03.07.2019 10:00
Health, 03.07.2019 10:00
Mathematics, 03.07.2019 10:00
Mathematics, 03.07.2019 10:00
Mathematics, 03.07.2019 10:00