The following is a table of activities associated with
a project at rafay ishfaq’s software firm in chicago, their durations,
and what activities each must precede:
activity duration (weeks) precedes
a (start) 1 b, c
b 1 e
c 4 f
e 2 f
f (end) 2 —
a) draw an aon diagram of the project, including activity durations.
b) define the critical path, listing all critical activities in chronological
order.
c) what is the project duration (in weeks)?
d) what is the slack (in weeks) associated with any and all noncritical
paths through the project?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:00
Brent wants to know what is 5 x 1/2
Answers: 2
question
Mathematics, 21.06.2019 20:00
The distribution of the amount of money spent by students for textbooks in a semester is approximately normal in shape with a mean of $235 and a standard deviation of $20. according to the standard deviation rule, how much did almost all (99.7%) of the students spend on textbooks in a semester?
Answers: 2
question
Mathematics, 21.06.2019 21:00
What is the value of m in the equation 1/2 m - 3/4n=16 when n=8
Answers: 1
question
Mathematics, 21.06.2019 23:10
Point s lies between points r and t on . if rt is 10 centimeters long, what is st? 2 centimeters 4 centimeters 6 centimeters 8 centimeters
Answers: 2
You know the right answer?
The following is a table of activities associated with
a project at rafay ishfaq’s software fi...
Questions
question
Mathematics, 03.06.2021 08:40
question
Mathematics, 03.06.2021 08:40
question
Chemistry, 03.06.2021 08:40
question
Mathematics, 03.06.2021 08:40
question
Physics, 03.06.2021 08:40
Questions on the website: 13722361