Processing times and due dates of 9 jobs are given as follows:
Job 1 2 3 4 5 6 7 8 9
Proc Ti...
Mathematics, 22.04.2021 20:00 eparikh7317
Processing times and due dates of 9 jobs are given as follows:
Job 1 2 3 4 5 6 7 8 9
Proc Time 4 3 7 9 8 15 6 7 10
Due Date 35 40 44 25 20 43 40 22 38
Assume that all jobs arrive at time 0
a) Generate a schedule that minimizes the mean flow time. Break ties with the smallest job number first (i. e., if 3 and 8 have identical parameters, 3 should be scheduled first).
b) Calculate mean flow time, mean tardiness, and maximum tardiness of the schedule obtained in a)
c) Generate a schedule that minimizes the maximum tardiness. Break ties with the smallest job number first.
d) Calculate mean flow time, mean tardiness, and maximum tardiness of the schedule obtained in c)
Answers: 1
Mathematics, 21.06.2019 19:00
You earn a 12% commission for every car you sell. how much is your commission if you sell a $23,000 car?
Answers: 1
Mathematics, 21.06.2019 21:00
Val and tony get paid per project. val is paid a project fee of $44 plus $12 per hour. tony is paid a project fee of $35 plus $15 per hour. write an expression to represent how much a company will pay to hire both to work the same number of hours on a project.
Answers: 1
Mathematics, 28.07.2021 08:10
Biology, 28.07.2021 08:20
Geography, 28.07.2021 08:20
Geography, 28.07.2021 08:20
Biology, 28.07.2021 08:20
Mathematics, 28.07.2021 08:20
English, 28.07.2021 08:20
English, 28.07.2021 08:20
Biology, 28.07.2021 08:20
Mathematics, 28.07.2021 08:20
Mathematics, 28.07.2021 08:20
Mathematics, 28.07.2021 08:20
Mathematics, 28.07.2021 08:20