The following information is available for the production of utils: STANDARDS

Ingredients Pounds Price per pound Total

A 400 $2 $800

B 800 4 3,200

C 800 6 ­4,800

Input 2,000

Output 1,500

ACTUAL RESULTS

Ingredients Pounds Price per pound

A 50,000 $2.10

B 60,000 3.95

C 90,000 7.00 ­

Input 200,000

Output 120,000

REQUIRED: Calculate the yield variance.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 18:00
The base of a triangle exceeds the height by 7 centimeters. if the area is 400 square centimeters, find the length of the base and the height of the triangle.
Answers: 1
question
Mathematics, 21.06.2019 18:30
Astick 2 m long is placed vertically at point b. the top of the stick is in line with the top of a tree as seen from point a, which is 3 m from the stick and 30 m from the tree. how tall is the tree?
Answers: 2
question
Mathematics, 21.06.2019 19:30
Ariel is working at a meat packing plant for 5 nights a week. her regular wage is $11 an hour. she earns tine and a half for any overtime hours. this week she worked 9 hours of over time .how much will ariel earn for overtime this week ?
Answers: 1
question
Mathematics, 21.06.2019 20:30
Solve each quadratic equation by factoring and using the zero product property. [tex]x^2+6x+8=0[/tex]
Answers: 2
You know the right answer?
The following information is available for the production of utils: STANDARDS

Ingredie...
Questions
question
Mathematics, 04.04.2020 00:01
question
Chemistry, 04.04.2020 00:01
Questions on the website: 13722363