45 workers can complete a piece of work in 12 days. how many workers should be removed so that it takes 6 more days to complete the work

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
Three cylinders have a volume of 2836 cm^3. cylinder a has a height of 900 cm. cylinder b has a height of 225 cm. cylinder c has a height of 100 cm. find the radius of each cylinder. use 3.14 as an approximate for ฯ€
Answers: 1
question
Mathematics, 21.06.2019 21:30
The anwser cause i do not understand just plez
Answers: 1
question
Mathematics, 22.06.2019 00:00
Plz hurry finals a paper cup in the shape of an inverted cone is 8 inches tall and has a radius of 1.5 inches. how much water can the cup hold? use 3.14 for pi. round the answer to the nearest tenth. a) 12.6 cubic in. b) 18.8 cubic in. c) 37.7 cubic in. d) 56.5 cubic in.
Answers: 2
question
Mathematics, 22.06.2019 01:30
Study results indicate that the mean length of time people spend on a bus in a city is between 21.2 min and 24.5 min what is the study margin of the error?
Answers: 1
You know the right answer?
45 workers can complete a piece of work in 12 days. how many workers should be removed so that it ta...
Questions
question
History, 30.08.2019 08:30
question
Mathematics, 30.08.2019 08:30
Questions on the website: 13722359