A heavy equipment manufacturing company has produced its first unit using 3500 hours and $300,000 overhead cost. The next unit, i. e. the second unit took 3300 hours. Overhead cost for this
unit was $200,000. Suppose the labor was $20 per hour. Being the production manager, you need
to decide what would be the total production costs for additional 10 units after the completi on of
the second unit. Round the final amount to nearest integer.
(A) $1,597,832
(B) $594,650
(C) $1,003,183
(D) None of the above

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 13:00
The measurement of one angle of a right triangle is 34°. what is the measurement of the third angle?
Answers: 1
question
Mathematics, 21.06.2019 14:00
Solve the system. -a+4b+2c=-8 3a+b-4c=9 b=-1 a.(0,11) ,-1,2) c.(1,1,-2) d.(2,-1,-1)
Answers: 1
question
Mathematics, 21.06.2019 18:00
When y’all answer can y’all explain too !
Answers: 1
question
Mathematics, 21.06.2019 18:30
The bake stars picked 907 apples last weekend at a local orchard they made caramel apples and sold them in the bakery in trays of 6
Answers: 1
You know the right answer?
A heavy equipment manufacturing company has produced its first unit using 3500 hours and $300,000...
Questions
question
History, 26.06.2019 17:00
Questions on the website: 13722360