Mathematics, 07.05.2021 01:20 DaePoggers
A small software development project consists of the following eight activities.
Activity Expected Time Critical Variance
A 4 4.0
B 5 Yes 3.0
C 2 0.0
D 4 Yes 1.0
E 5 Yes 1.0
F 8 4.0
G 6 Yes 1.25
H 2 0.0
Required:
a. Specify the Project Completion Time and the Standard Deviation.
b. Calculate the z value.
c. What is the probability of completing the project in 23 weeks or less
Answers: 3
Mathematics, 21.06.2019 18:20
The length of a rectangle plus its width is 25 cm. the area is 156 square cm. what are the length and width of the rectangle? separate the answers with a comma.
Answers: 3
Mathematics, 21.06.2019 22:10
Acompany manufactures three types of cabinets. it makes 110 cabinets each week. in the first week, the sum of the number of type-1 cabinets and twice the number of type-2 cabinets produced was 10 more than the number of type-3 cabinets produced. the next week, the number of type-1 cabinets produced was three times more than in the first week, no type-2 cabinets were produced, and the number of type-3 cabinets produced was the same as in the previous week.
Answers: 1
Mathematics, 21.06.2019 23:00
Solve the system of equations using the substitution method. {y=−3x+7x=−2y−16 enter your answers in the boxes.
Answers: 1
A small software development project consists of the following eight activities.
Activity Expected...
Spanish, 21.02.2020 03:54
Biology, 21.02.2020 03:54