689 To complete a task in 16 days a company needs
5 people each working for 6 hours per day.
The company decides to have
8 people each working for 4 hours per day.
Assuming that each person works at the same rate,
how many days will the task take to complete?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 14:10
5500 dollars is placed in an account with an annual interest rate of 6.5%. to the nearest tenth of a year, how long will it take for the account value to reach 19700 dollars?
Answers: 2
question
Mathematics, 21.06.2019 16:00
Which fraction is not equivalent to 8/12 a. 2/3 b. 24/36 c. 4/10 d. 6/10
Answers: 1
question
Mathematics, 21.06.2019 22:20
Let f(x) = 5/x and g(x)=2x2+5x. what two numbers are not in the domain of f o g
Answers: 2
question
Mathematics, 22.06.2019 00:00
This summer the number of tourists in salem increased 4.5% from last years total of 426000. how many more tourists came to salem this summer
Answers: 1
You know the right answer?
689 To complete a task in 16 days a company needs
5 people each working for 6 hours per day.<...
Questions
question
Mathematics, 01.02.2021 09:00
question
English, 01.02.2021 09:00
question
Mathematics, 01.02.2021 09:00
Questions on the website: 13722361