Completion time (from start to finish) of a building remodeling project is normally distributed with a mean of 200 work days and a standard deviation of 10 workdays. To be 99% sure that you will not be late in completing the project, you should request a completion time of workdays.

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 15:40
36 inches/second = yards/minute how many yards?
Answers: 1
question
Mathematics, 21.06.2019 18:30
Use the four functions below for this question. compare and contrast these four functions using complete sentences focus on the slope and y- intercept first, and then on any additional properties of each function
Answers: 3
question
Mathematics, 21.06.2019 19:00
Find the length of the diagonal of the rectangle. round your answer to the nearest tenth. || | | 8 m | | | | 11 m
Answers: 2
question
Mathematics, 21.06.2019 19:30
Find the commission on a $590.00 sale if the commission is 15%.
Answers: 2
You know the right answer?
Completion time (from start to finish) of a building remodeling project is normally distributed with...
Questions
question
Computers and Technology, 01.07.2019 23:30
question
Business, 01.07.2019 23:30
Questions on the website: 13722362