41. The number of days it takes a movie crew to set up a stage varies inversely as the number of workers. If the stage can be set up in 3 days by 20 workers, how
many days would it take if only 12 workers were available?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 21:30
Look at triangle wxy what is the length (in centimeters) of the side wy of the triangle?
Answers: 1
question
Mathematics, 21.06.2019 22:00
The sum of the speeds of two trains is 720.2 mph. if the speed of the first train is 7.8 mph faster than the second train, find the speeds of each.
Answers: 1
question
Mathematics, 21.06.2019 22:20
Question 5 of 10 2 points if a population is a sample of the population could be a. registered voters; all citizens o o b. baptists; all religious people o c. people who purchased shoes; all customers o d. the entire school faculty; math teachers
Answers: 3
question
Mathematics, 21.06.2019 22:30
Awoman has 14 different shirts: 10 white shirts and 4 red shirts. if she randomly chooses 2 shirts to take with her on vacation, then what is the probability that she will choose two white shirts? show your answer in fraction and percent, round to the nearest whole percent.
Answers: 1
You know the right answer?
41. The number of days it takes a movie crew to set up a stage varies inversely as the number of wo...
Questions
question
Mathematics, 21.05.2020 04:02
question
Mathematics, 21.05.2020 04:02
question
Mathematics, 21.05.2020 04:02
Questions on the website: 13722359