12 workers can do a piece of work in 20 days, how many worker should
be added to complete the work in 16 days? [Ans: 3]

If you help me to do this question I will make brainliest​

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
What term makes it inconsistent y=2x - 4
Answers: 3
question
Mathematics, 21.06.2019 18:00
Janie has $3. she earns $1.20 for each chore she does and can do fractions of chores. she wants to earn enough money to buy a cd for $13.50. write an inequality to determine the number of chores, c, janie could do to have enough money to buy the cd.
Answers: 1
question
Mathematics, 21.06.2019 18:30
Which of the following is the true for f(x) = 5cos
Answers: 2
question
Mathematics, 21.06.2019 19:00
Which shows the correct substitution of the values a,b and c from the equation 1=-2x+3x^2+1
Answers: 1
You know the right answer?
12 workers can do a piece of work in 20 days, how many worker should
be added to complete the...
Questions
question
Mathematics, 28.06.2019 22:00
Questions on the website: 13722367