A and B take M days to complete a task together if A takes 27 days more than A and B to complete the task alone. And if B takes 3 days more than A and B can do the job alone, what is the value of M?​

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 18:30
Tod does not have any cookies. david gives jeff 8 cookies. then he splits half of the cookies he has left with tod. david let’s c represent the number of cookies that he starts with. he finds the number of cookies that tod has is 1/2 the difference of c and 8. write an expression to represent the number of cookies that tod has.
Answers: 2
question
Mathematics, 21.06.2019 19:50
Which of the following describes the graph of y--4x-36 compared to the parent square root function? stretched by a factor of 2, reflected over the x-axis, and translated 9 units right stretched by a factor of 2, reflected over the x-axis, and translated 9 units left stretched by a factor of 2, reflected over the y-axis, and translated 9 units right stretched by a factor of 2, reflected over the y-axis, and translated 9 units left save and exit next submit
Answers: 1
question
Mathematics, 21.06.2019 20:00
Donald has x twenty-dollar bills and 11 ten-dollar bill. how much money does donald have? write your answer as an expression.
Answers: 2
question
Mathematics, 21.06.2019 21:00
Rewrite the following quadratic functions in intercept or factored form. show your work. f(x) = 3x^2 - 12
Answers: 1
You know the right answer?
A and B take M days to complete a task together if A takes 27 days more than A and B to complete the...
Questions
question
Biology, 04.02.2020 03:46
question
Health, 04.02.2020 03:46
Questions on the website: 13722361