Mathematics, 22.06.2021 14:50 melkumathurin

20 men can do a piece of work in 24 days. After working for few days, 3 men are added and the work was finished 3 days earlier. After how many days if 4 men are added?​

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:30
Apositive number a or the same number a increased by 50% and then decreased by 50% of the result?
Answers: 3
question
Mathematics, 21.06.2019 22:00
Iam at home. /: i am playing video games. translate the following statement into symbolic form.
Answers: 2
question
Mathematics, 21.06.2019 23:30
Segment wx is shown explain how you would construct a perpendicular bisector of wx using a compass and a straightedge
Answers: 3
question
Mathematics, 22.06.2019 00:00
Cody ran nine miles on his first day of training. the next day he ran 1/8 that distance. how far did he run the second day?
Answers: 2
You know the right answer?
20 men can do a piece of work in 24 days. After working for few days, 3 men are added and the work w...
Questions
question
Mathematics, 29.03.2020 01:56
question
Mathematics, 29.03.2020 01:57
question
English, 29.03.2020 01:57
question
Mathematics, 29.03.2020 01:57
question
Biology, 29.03.2020 01:57
Questions on the website: 13722363