A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs.200 for the first day, Rs.250 for the second day, Rs.300 for the third day, etc.., The penalty for each succeeding day being Rs.50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days??​

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 20.06.2019 18:04
Order the numbers in each list from least to greatest. 0, |βˆ’14|, 13, βˆ’12, |βˆ’16|, 17
Answers: 2
question
Mathematics, 21.06.2019 16:50
What is the perimeter of square abcd? units units 28 units 37 units
Answers: 2
question
Mathematics, 21.06.2019 17:30
Find the exact value of each of the following. in each case, show your work and explain the steps you take to find the value. (a) sin 17Ο€/6 (b) tan 13Ο€/4 (c) sec 11Ο€/3
Answers: 2
question
Mathematics, 21.06.2019 19:00
Quadrilateral abcd in the figure below represents a scaled-down model of a walkway around a historic site. quadrilateral efgh represents the actual walkway. abcd is similar to efgh. what is the total length, in feet of the actual walkway?
Answers: 2
You know the right answer?
A contract on construction job specifies a penalty for delay of completion beyond a certain date as...
Questions
Questions on the website: 13722367