Question 4 (5 marks) To restore a vintage train, 13 activities need to be completed. The network below shows these 13 activities and their completion times in hours. C,6 G, 3 4,5 1D, 2 H,4 K,7 E, 2 L, 3 start finish B, 5 F,4 1,3 *M,6 J, 2 a. Determine the earliest starting time of activity F.

The minimum time in which all 13 activities can be completed is 21 hours.
b. What is the latest starting time of activity L?

C. What is the float time of activity J?

Just before they started restoring the train, the members of the club needed to add another activity, X, to the project Activity X will take seven hours to complete. Activity X has no predecessors, but must be completed before activity G starts.
d. What is the latest starting time of activity Xif it is not to increase the minimum completion time of the project? 1 markโ€‹

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 14:50
What is the inverse of the function f(x) = 2x + 1?
Answers: 1
question
Mathematics, 21.06.2019 17:30
Scrub a dub toothbrushes are $4.00 each. there is a 10% discount, but there is also a 6% sales tax after the discount is applied. what is the new price after tax? round to the nearest penny
Answers: 1
question
Mathematics, 21.06.2019 18:40
This stem-and-leaf plot represents the heights of the students on ralph's basketball team. one student's height is missing from the plot. if the mean height of all the students on the team is 61 inches, what is the missing height? a. 55 in. b. 59 in. c. 61 in. d. 65 in.
Answers: 2
question
Mathematics, 21.06.2019 22:20
Jimmy can run 3.5 miles in 20 minutes. how far can ne run in one hour and ten minutes?
Answers: 1
You know the right answer?
Question 4 (5 marks) To restore a vintage train, 13 activities need to be completed. The network bel...
Questions
question
Mathematics, 19.08.2019 08:30
question
Mathematics, 19.08.2019 08:30
question
Mathematics, 19.08.2019 08:30
Questions on the website: 13722359