What is the maximum number of hours that the completion time of a critical activity can be reduced without changing the critical path of the project?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 20.06.2019 18:02
Anew fountain in the shape of a hexagon will have 6 sides of equal length. on a scale drawing, the coordinates of the vertices of the fountain are: (7.5,5), (11.5,2), (7.5,βˆ’1), (2.5,βˆ’1), (βˆ’1.5,2), and (2.5,5). how long is each side of the fountain?
Answers: 3
question
Mathematics, 21.06.2019 19:30
Complete the solution of the equation. find the value of y when x equals to 28 x+3y=28
Answers: 2
question
Mathematics, 21.06.2019 20:30
A. plot the data for the functions f(x) and g(x) on a grid and connect the points. x -2 -1 0 1 2 f(x) 1/9 1/3 1 3 9 x -2 -1 0 1 2 g(x) -4 -2 0 2 4 b. which function could be described as exponential and which as linear? explain. c. if the functions continue with the same pattern, will the function values ever be equal? if so, give estimates for the value of x that will make the function values equals. if not, explain why the function values will never be equal.
Answers: 3
question
Mathematics, 21.06.2019 21:00
Dean and karlene get paid to write songs. dean is paid a one-time fee of $20 plus $80 per day. karlene is paid a one-time fee of $25 plus $100 per day. write an expression to represent how much a producer will pay to hire both to work the same number of days on a song.
Answers: 1
You know the right answer?
What is the maximum number of hours that the completion time of a critical activity can be reduced w...
Questions
question
Chemistry, 06.11.2020 17:30
Questions on the website: 13722367