To complete a task in 16 days a company needs 5 people each working for 6 hours a day
The company decides to have
8 people each working for 4 hours a day

Assuming that each person works at the same rate, how many days will the task take to complete?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
Which fraction below is equivalent to 10/12?
Answers: 3
question
Mathematics, 21.06.2019 16:00
Find x to the nearest hundredth place
Answers: 2
question
Mathematics, 21.06.2019 17:30
Adriver from the university of florida women’s swimming and diving team is competing in the in ncaa zone b championships
Answers: 3
question
Mathematics, 21.06.2019 18:00
Name each raycalculation tip: in ray "ab", a is the endpoint of the ray.
Answers: 2
You know the right answer?
To complete a task in 16 days a company needs 5 people each working for 6 hours a day
The co...
Questions
question
Mathematics, 06.04.2021 18:10
question
Mathematics, 06.04.2021 18:10
Questions on the website: 13722363