Choose the correct answer. The time to complete a project varies inversely with the number of employees. If 6 people can complete the project in 4 days, how long will it take 8 people?

A. 5 days
B. 3 days
C. 2 days
D. 6 days

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 20:40
The roots of the function f(x) = x2 – 2x – 3 are shown. what is the missing number?
Answers: 2
question
Mathematics, 21.06.2019 22:00
20 points 1. your friend, taylor, missed class today and needs some identifying solutions to systems. explain to taylor how to find the solution(s) of any system using its graph. 2. taylor graphs the system below on her graphing calculator and decides that f(x)=g(x) at x=0, x=1, and x=3. provide taylor some feedback that explains which part of her answer is incorrect and why it is incorrect. f(x)=2x+1 g(x)=2x^2+1
Answers: 2
question
Mathematics, 21.06.2019 22:00
State one method by which you can recognize a perfect square trinomial.
Answers: 1
question
Mathematics, 22.06.2019 00:00
Cd is the perpendicular bisector of both xy and st, and cy=20. find xy.
Answers: 1
You know the right answer?
Choose the correct answer. The time to complete a project varies inversely with the number of empl...
Questions
question
Mathematics, 28.02.2020 22:22
question
Chemistry, 28.02.2020 22:23
Questions on the website: 13722361