(Unitary Method) 12 workers can do a piece of work in 20 days. How many workers should be added to complete the work in 16 days?
(Give answer in process by process)
(Answer is 3 workers)

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 19:30
Ineed with this problem 21 show steps
Answers: 2
question
Mathematics, 21.06.2019 21:30
Aroulette wheel has 38 slots in which the ball can land. two of the slots are green, 18 are red, and 18 are black. the ball is equally likely to land in any slot. the roulette wheel is going to be spun twice, and the outcomes of the two spins are independent.the probability that it lands one time on red and another time on black in any order is(a) 0.5 (b) 0.25 (c) 0.4488 (d) 0.2244
Answers: 1
question
Mathematics, 21.06.2019 23:20
For which pairs of functions is (fโ€ขg)(x)=12x? f(x)=3-4x and g(x)=16x-3 f(x)=6x2 and g(x)= 2/x f(x)= and g(x) = 144x f(x)=4x and g(x) =3x
Answers: 1
question
Mathematics, 22.06.2019 00:00
The amount of data left on the cell phone six gb for 81.5 gb of data is used how much data is available at the beginning of the cycle
Answers: 2
You know the right answer?
(Unitary Method) 12 workers can do a piece of work in 20 days. How many workers should be added to...
Questions
question
Mathematics, 10.10.2019 17:00
question
Social Studies, 10.10.2019 17:00
Questions on the website: 13722367