In this question assume that all the men work for the same hours and at the same work rate.
A builder estimates 5 men would need 12 days to complete the job.
What would his estimate be for 4 men to complete the same job?
You must show your working.

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 16:00
Find the solution set of this inequality. select the correct graph. |8x+16|> 16
Answers: 1
question
Mathematics, 21.06.2019 19:00
What is the explicit formula for this sequence? -7, -4, -1, 2, a.) an = 8 + (b - 1)3 b.) an = -7 + (n - 1)3 c.) an = 3 + (n -1) (-7) d.) an = -7 + (n - )
Answers: 1
question
Mathematics, 21.06.2019 20:00
How to find the exponential function y=ca^x, with points (1,2) and (2,1)
Answers: 2
question
Mathematics, 22.06.2019 00:20
Once george got to know adam, they found that they really liked each other. this is an example of what factor in friendship
Answers: 1
You know the right answer?
In this question assume that all the men work for the same hours and at the same work rate.
...
Questions
question
Arts, 08.04.2021 02:50
question
English, 08.04.2021 02:50
question
Law, 08.04.2021 02:50
Questions on the website: 13722361