What is the probability of finishing a project on or before 22 weeks if the mean (expected) total duration is 18 weeks and the variance is 4 weeks?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 18:30
The formula for the lateral area of a right cone is la = rs, where r is the radius of the base and s is the slant height of the cone.which are equivalent equations?
Answers: 3
question
Mathematics, 21.06.2019 22:10
Using graph paper, determine the line described by the given point and slope. click to show the correct graph below.(0, 0) and 2/3
Answers: 2
question
Mathematics, 21.06.2019 23:20
8litres of paint can cover 129.6 m². how much paint is required to paint an area of 243m²?
Answers: 3
question
Mathematics, 21.06.2019 23:30
Bonnie and bobby are saving money for a vacation. each friend starts with an amount and also saves a specific amount each week. bonnie created a table to show the total she has saved at the end of each week.. weeks 0 1 2 3 4 5 6 7 8 amount saved 12 16 20 24 28 32 36 40 44 bobby came up with the following equation to show the total, y, he has saved at the end of each week, x. y = 12x + 4 compare the rate at which each friend saves money. select the correct answer from the drop-down menu to complete the statement. the rate at which bobby is adding to his savings each week is $ more than the rate at which bonnie is adding to her savings each week.
Answers: 2
You know the right answer?
What is the probability of finishing a project on or before 22 weeks if the mean (expected) total du...
Questions
question
Mathematics, 13.12.2021 04:10
question
Mathematics, 13.12.2021 04:10
question
Social Studies, 13.12.2021 04:10
question
Chemistry, 13.12.2021 04:10
Questions on the website: 13722367