Mathematics, 31.07.2019 11:30 kadariusmerchan

Three workers can do a job in 28 hours. how many more workers are needed to do this job in 12 hours?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 23:30
Find │–14│ a. 14 b. –14 c. start fraction 1 over 14 end fraction
Answers: 2
question
Mathematics, 22.06.2019 01:00
How would you find the height of points on the circle? the topic is trigonometry.
Answers: 3
question
Mathematics, 22.06.2019 02:00
1. solve the system of equations by graphing: y = -3x - 3 m = b = y = 2x + 2 m = b = plz solve now
Answers: 1
question
Mathematics, 22.06.2019 02:00
Acompany had forty one employees and ordered nine hundred eighty uniforms for them. if they wanted to give each employees the same number of uniforms, how many more uniforms should they order so they don't have any extra
Answers: 1
You know the right answer?
Three workers can do a job in 28 hours. how many more workers are needed to do this job in 12 hours?...
Questions
question
Mathematics, 30.11.2020 22:50
Questions on the website: 13722359