9workers working 8 hours a day to complete a piece of work in 52 days. how long will it take 13 workers to complete the same job by working 6 hours a day? show all the steps. correct answer will get brainliest

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 19:30
Bobby bought 1.12 pounds of turkey at a cost of 2.50 per pound. carla bought 1.4 pounds of turkey at a cost of 2.20 per pound. who spent more and by much?
Answers: 2
question
Mathematics, 21.06.2019 20:40
Lines a and b are parallel. what is the value of x? -5 -10 -35 -55
Answers: 2
question
Mathematics, 21.06.2019 21:30
Find the missing dimension! need asap! tiny square is a =3025 in Β²
Answers: 1
question
Mathematics, 21.06.2019 23:00
What is the sum of the first 8 terms of the geometric series
Answers: 3
You know the right answer?
9workers working 8 hours a day to complete a piece of work in 52 days. how long will it take 13 work...
Questions
question
History, 11.12.2019 06:31
question
Mathematics, 11.12.2019 06:31
question
Mathematics, 11.12.2019 06:31
question
Mathematics, 11.12.2019 06:31
question
History, 11.12.2019 06:31
Questions on the website: 13722367