Mathematics, 18.08.2019 16:20 khalilah2000ortbfy

Six workers can do 9 identical jobs in 3 days. how long will it take 4 workers to do 10 such jobs
a) 3 days
b) 4 days
c) 5 days
d) 6 days
e) more than 6 days
i guess it's ans is d.

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
Suppose i flip two identical coins. what is the probability that i get one head and one tail?
Answers: 2
question
Mathematics, 21.06.2019 18:20
The length of a rectangle plus its width is 25 cm. the area is 156 square cm. what are the length and width of the rectangle? separate the answers with a comma.
Answers: 3
question
Mathematics, 21.06.2019 22:20
The mean of 10 values is 19. if further 5 values areincluded the mean becomes 20. what is the meanthese five additional values? a) 10b) 15c) 11d) 22
Answers: 1
question
Mathematics, 21.06.2019 22:40
20.ju inces. which ordered pair is a viable solution if x represents the number of books he orders and y represents the total weight of the books, in ounces? (-3,-18) (-0.5, -3) (0,0) (0.5, 3)
Answers: 1
You know the right answer?
Six workers can do 9 identical jobs in 3 days. how long will it take 4 workers to do 10 such jobs
Questions
question
History, 30.08.2019 02:30
Questions on the website: 13722360