Social Studies, 18.10.2020 21:01 mccdp55
A project consists of 8 activities. The activity completion times and the precedence relationships are as follows:
Activity. Completion time Days. immediate predecessor activities.
A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F
1. Draw the network diagram using AON model notations:
2. What is the critical path?
3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.
4. What is the minimum time to complete the projects?
1. If activity E is delayed by 3 days how is the project completion time affected? Why is this the case?
2. If activity F is delayed by 3 days how is the project completion time affected? Why is this the case? Will the critical path change, why or why not?
3. If you want to shorten (crash) the overall time of this project, how do you pick which activity to shorten? What information, if any, do you need?
4. Once you shorten (crash) an activity, do you need to redo the AON, yes or no? Why or why not?
Answers: 2
Social Studies, 22.06.2019 17:30
Giving into indirect pressure to change your behavior or thoughts is called?
Answers: 1
Social Studies, 22.06.2019 18:00
The buddhaβs teachings were influenced by other religions. select the best answer from the choices provided t f
Answers: 1
Social Studies, 22.06.2019 18:30
Which of the following best summarizes the idea represented by this graph?
Answers: 2
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Physics, 03.01.2020 17:31
Mathematics, 03.01.2020 17:31
History, 03.01.2020 17:31
Mathematics, 03.01.2020 17:31
Mathematics, 03.01.2020 17:31
History, 03.01.2020 17:31
English, 03.01.2020 17:31
History, 03.01.2020 17:31
History, 03.01.2020 17:31
Mathematics, 03.01.2020 17:31
Spanish, 03.01.2020 17:31
Geography, 03.01.2020 17:31