15. A contract on construction job specifies a penalty for delay of completion beyond a
certain date as follows: 200 for the first day, 7 250 for the second day, 300 for the third
day, etc., the penalty for each succeeding day being ? 50 more than for the preceding day
How much money the contractor has to pay as penalty, if he has delayed the work by 30
days 2