15. A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: 200 for the first day, 7 250 for the second day, 300 for the third
day, etc., the penalty for each succeeding day being ? 50 more than for the preceding day
How much money the contractor has to pay as penalty, if he has delayed the work by 30
days 2

ansver
Answers: 3

Another question on Spanish

question
Spanish, 23.06.2019 03:30
Words to ask what others like to do in spanish
Answers: 2
question
Spanish, 23.06.2019 15:00
La lengua de los inca y de muchos peruanos indígenas es a. el español c. b. el inca d. el quechua el ande
Answers: 2
question
Spanish, 23.06.2019 19:30
Su casa no está lejos de la escuela. está
Answers: 2
question
Spanish, 24.06.2019 09:10
La señora ferrer es la madre de mayte y rosita. mayte y rosita son de la señora ferrer.
Answers: 2
You know the right answer?
15. A contract on construction job specifies a penalty for delay of completion beyond a certain dat...
Questions
Questions on the website: 13722361