Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value. EV is the earned value, AC is the actual cost, and BAC is the budget at completion.
PV = $23,000
EV = $20,000
AC = $25,000
BAC = $120,000
a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
d. Use the schedule performance index (SPI) to estimate how long it will take to finish this project.
e. Sketch the earned value chart based on this project

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 09:40
Wilson center is a private not-for-profit voluntary health and welfare entity. during 2017, it received unrestricted pledges of $638,000, 65 percent of which were payable in 2017, with the remainder payable in 2018 (for use in 2018). officials estimate that 14 percent of all pledges will be uncollectible. a. how much should wilson center report as contribution revenue for 2017? b. in addition, a local social worker, earning $20 per hour working for the state government, contributed 600 hours of time to wilson center at no charge. without these donated services, the organization would have hired an additional staff person. how should wilson center record the contributed service?
Answers: 2
question
Business, 22.06.2019 11:10
Suppose that the firm cherryblossom has an orchard they are willing to sell today. the net annual returns to the orchard are expected to be $50,000 per year for the next 20 years. at the end of 20 years, it is expected the land will sell for $30,000. calculate the market value of the orchard if the market rate of return on comparable investments is 16%.
Answers: 1
question
Business, 22.06.2019 16:10
From what part of income should someone take savings?
Answers: 2
question
Business, 22.06.2019 17:30
An essential element of being receptive to messages is to have an open mind true or false
Answers: 2
You know the right answer?
Given the following information for a one-year project, answer the following questions. Recall that...
Questions
question
Mathematics, 14.11.2019 19:31
Questions on the website: 13722360