Shipments of Product X from a plant to a wholesaler are made in lots of 600. The wholesaler's average demand for X is 100 units per week. Lead time from plant to wholesaler is 4 weeks. The wholesaler pays for the shipments when they leave the plant.
Refer to the instruction above. If the plant reduces its lead time from 4 to 2 weeks and keeps its 600 unit lot size, what is the wholesaler's new total cycle plus pipeline inventories?
A) 300 units
B) 500 units
C) 700 units
D) 200 units
Answers: 1
Business, 21.06.2019 16:00
Jelly has joined drakes team drake sends kelly an email explaining details of the project that she will be working on which of these is good etiquette
Answers: 3
Business, 22.06.2019 01:50
Which statement below best describes george waring's approach to solving the problems of water-borne illness? a. waring is going with his "gut," because he believes that instincts and emotions are the best guides for action. b. waring efficiently and thoroughly lays out the case for why the problems are too large and overwhelming to be solved: people should just move out of cities back to their farms. c. waring has gathered the testimonies of people who live in densely populated areas in order to learn how they themselves have solved their problems. d. waring exhibits the industrial age's increased respect for and reliance on science and the scientific method.
Answers: 1
Business, 22.06.2019 10:20
Asmartphone manufacturing company uses social media to achieve different business objectives. match each social media activity of the company to the objective it the company achieve.
Answers: 3
Business, 22.06.2019 19:30
Do a swot analysis for the business idea you chose in question 2 above. describe at least 2 strengths, 2 weaknesses, 2 opportunities, and 2 threats for that company idea.
Answers: 2
Shipments of Product X from a plant to a wholesaler are made in lots of 600. The wholesaler's averag...
Mathematics, 12.07.2019 06:00
History, 12.07.2019 06:00
Business, 12.07.2019 06:00
Mathematics, 12.07.2019 06:00