A proposed nuclear power plant will cost $2.2 billion to build and then will produce cash flows of $300 million a year for 15 years. After that period (in year 15), it must be decommissioned at a cost of $900 million. (LO8-1 and LO8-2)

a. What is project NPV if the discount rate is 5%?

b. What if the discount rate is 18%?

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 11:30
Mark knopf is an auditor who has been asked to provide an audit and financial statement certification for a company that is going public on the new york stock exchange. knopf wants to know his personal liability if the company provides him with inaccurate or false information. which of the following sources of law will him answer that question? a. the city ordinances where the company headquarters is located. b. the state constitution of the state where the company is incorporated. c. code of federal regulations. d. all of the above
Answers: 1
question
Business, 22.06.2019 14:00
Bayside coatings company purchased waterproofing equipment on january 2, 20y4, for $190,000. the equipment was expected to have a useful life of four years and a residual value of $9,000. instructions: determine the amount of depreciation expense for the years ended december 31, 20y4, 20y5, 20y6, and 20y7, by (a) the straight-line method and (b) the double-declining-balance method. also determine the total depreciation expense for the four years by each method. depreciation expense year straight-line method double-declining-balance method 20y4 $ $ 20y5 20y6 20y7 total $
Answers: 3
question
Business, 22.06.2019 21:10
Acompany has two products: standard and deluxe. the company expects to produce 36,375 standard units and 62,240 deluxe units. it uses activity-based costing and has prepared the following analysis showing budgeted cost and cost driver activity for each of its three activity cost pools.budgeted activity of cost driver activity cost pool budgeted cost standard deluxe activity 1 $ 93,000 2,500 5,250 activity 2 $ 92,000 4,500 5,500 activity 3 $ 87,000 3,000 2,800 what is the overhead cost per unit for the standard units? what is the overhead cost per unit for the deluxe units? (round activity rate and cost per unit answers to 2 decimal places.)activity expected costs expected activity driver activity rate1 93,000 2 92,000 3 87,000 standard activity activity driver activity rate allocated costs1 2 3
Answers: 2
question
Business, 22.06.2019 23:40
When randy, a general manager of a national retailer, moved to a different store in his company that was having difficulty, he knew that sales were low and after talking to his employees, he found morale was also low. at first randy thought attitudes were poor due to low sales, but after working closely with employees, he realized that the poor attitudes were actually the cause of poor sales. randy was able to discover the cause of the problem by utilizing skills.
Answers: 2
You know the right answer?
A proposed nuclear power plant will cost $2.2 billion to build and then will produce cash flows of $...
Questions
question
Mathematics, 23.01.2022 08:00
question
Computers and Technology, 23.01.2022 08:00
question
Mathematics, 23.01.2022 08:00
Questions on the website: 13722367