What is the normal project completion time, given the information above? The following information is given for a CPM network: Activity Predecessor Successor Normal Time Normal Cost Crash Time Crash Cost A --- B, C 5 $ 60 2 $ 125 B A D, C 4 70 2 90 C A, B D 6 80 3 150 D B, C --- 3 40 1 60

a. A-B-D.
b. Not enough information is provided.
c. A-C-D.
d. A-B-C-D.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 12:20
In terms of precent, beer has more alcohol than whiskey true or false
Answers: 1
question
Business, 22.06.2019 12:30
Sales at a fast-food restaurant average $6,000 per day. the restaurant decided to introduce an advertising campaign to increase daily sales. to determine the effectiveness of the advertising campaign, a sample of 49 days of sales were taken. they found that the average daily sales were $6,300 per day. from past history, the restaurant knew that its population standard deviation is about $1,000. if the level of significance is 0.01, have sales increased as a result of the advertising campaign? multiple choicea)fail to reject the null hypothesis.b)reject the null hypothesis and conclude the mean is higher than $6,000 per day.c)reject the null hypothesis and conclude the mean is lower than $6,000 per day.d)reject the null hypothesis and conclude that the mean is equal to $6,000 per day.expert answer
Answers: 3
question
Business, 22.06.2019 20:50
Barbara flynn is in charge of maintaining hospital supplies at general hospital. during the past year, the mean lead time demand for bandage bx-5 was 65 (and was normally distributed). furthermore, the standard deviation for bx-5 was 6. ms. flynn would like to maintain a 90% service level.refer to the standard normal table for z-values.a) what safety stock level do you recommend for bx-5? safety stock=)what is the appropriate reorder point? reorder point=
Answers: 1
question
Business, 22.06.2019 21:40
Which of the following distribution systems offers speed and reliability when emergency supplies are needed overseas? a. railroadsb. airfreightc. truckingd. pipelinese. waterways
Answers: 2
You know the right answer?
What is the normal project completion time, given the information above? The following information i...
Questions
question
Spanish, 24.09.2019 08:50
question
Mathematics, 24.09.2019 08:50
question
Mathematics, 24.09.2019 08:50
Questions on the website: 13722363