In each of the following MCQs please check the BEST correct answers. A. Resource utilization charts based on each activity's earliest start time are said to be based:.
a. on availability times.
b. an as-late-as-possible (ALAP) schedule.
c. on an as-soon-as-possible (ASAP) schedule.
d. on a limited schedule plan.
B. Resource leveling, or smoothing is a method for:.
a. developing a schedule that attempts to minimize the fluctuations in requirements for resources.
b. making sure all the resources do the same amount of work.
c. making sure every task has the same number of resources.
d. extending the project to have the least number of resources used per day.
C. A resource requirements plan illustrates:.
a. who is responsible for which activities.
b. the amount of labor expenses for the project.
c. the expected utilization of resources by time period during the time span of the project.
d. the budget for material and cost resources.
D. When several activities need the same limited resource at the same time, the activities with:.
a. the least slack have first priority.
b. the longest duration have first priority.
c. the near term have first priority.
d. use the most resources have first priority
E. In resource- limited scheduling, the lower priority activities get delayed. How does the delaying of activities affect the project?
a. The delaying of activities increases the costs of the project.
b. The delaying of activities decreases the acceptance of the project deliverable.
c. The delaying of activities may delay the project.
d. The delaying of activities helps give others more time on their tasks because they won't aff ect the project schedule.
F. The project scope is all the work that must be done to do all of the following except:.
a. meet with every stakeholder.
b. produce all the project deliverables.
c. accomplish the project objective.
d. satisfy the sponsor or customer that all the work and deliverables meet the requirements or acceptance criteria.
G. The major work elements defined in the statement of work section along with the detailed list of deliverables provide the basis for creating a:.
a. statement of work.
b. project scope document.
c. network diagram.
d. work breakdown structure.
H. It is common to progressively elaborate the network diagram:.
a. as the network diagram is being built the first time.
b. at the onset of the project.
c. as the project progresses and more information is known or becomes clear.
d. at the end of the project.
The project plan is executed in the:.
a. initiating phase.
b. planning phase.
c. performing phase.
d. closing phase d.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 21:50
Discuss how the resource-based view (rbv) of the firm combines the two perspectives of (1) an internal analysis of a firm and (2) an external analysis of its industry and its competitive environment. include comments on the different types of firm resources and how these resources can be used by a firm to build sustainable competitive advantages.
Answers: 3
question
Business, 22.06.2019 13:10
Thomas kratzer is the purchasing manager for the headquarters of a large insurance company chain with a central inventory operation. thomas's fastest-moving inventory item has a demand of 6,000 units per year. the cost of each unit is $100, and the inventory carrying cost is $10 per unit per year. the average ordering cost is $30 per order. it takes about 5 days for an order to arrive, and the demand for 1 week is 120 units. (this is a corporate operation, and the are 250 working days per year.)a) what is the eoq? b) what is the average inventory if the eoq is used? c) what is the optimal number of orders per year? d) what is the optimal number of days in between any two orders? e) what is the annual cost of ordering and holding inventory? f) what is the total annual inventory cost, including cost of the 6,000 units?
Answers: 3
question
Business, 22.06.2019 15:50
Evaluate a real situation between two economic actors; it could be any scenario: two competing businesses, two countries in negotiations, two kids trading baseball cards, you and another person involved in an exchange or anything else. use game theory to analyze the situation and the outcome (or potential outcome). be sure to explain the incentives, benefits and risks each face.
Answers: 1
question
Business, 22.06.2019 19:00
Describe how to write a main idea expressed as a bottom-line statement
Answers: 3
You know the right answer?
In each of the following MCQs please check the BEST correct answers. A. Resource utilization charts...
Questions
question
Business, 05.12.2021 22:30
question
Mathematics, 05.12.2021 22:30
question
Mathematics, 05.12.2021 22:40
Questions on the website: 13722359