Positively Rivet Inc. is a small machine shop that produces sheet metal products. It had one line dedicated to the manufacture of light-duty vent hood shells, but because of strong demand it recently added a second line. The new line makes use of higher-capacity automated equipment but consists of the same basic four processes as the old line. In addition, the new line makes use of one machine per workstation, while the old line has parallel machines at the workstations. The processes, along with their machine rates, number of machines per station, and average times for a lone job to go through a station (not including queue time), are provided below. Over the past 3 months, the old line has averaged 350 parts per day, where one day consists of one 8-hour shift, and has had an average WIP level of 400 parts. The new line has averaged 680 parts per eight-hour day with an average WIP level of 350 parts. Management has been dissatisfied with the performance of the old line because it is achieving lower throughput with higher WIP than the new line, Your job is to evaluate these two lines to the extent possible with the data provided and identify potentially attractive improvement paths for each line by addressing the following questions: Compute rb, To, and Wo for both lines. Which line has larger critical WIP? Explain why.
Compute the best case and worst case performance benchmarks for the old and the new line.
Compare the performance of both lines to their corresponding practical worst case. What can you conclude about the relative performance of the two lines compared to their underlying capabilities? Is management correct in criticizing the old line for inefficiency?
If you were the manager in charge of these lines, what option would you consider first to improve the throughput of the old line? Of the new line?
Old Line
Process Rate per Machine (parts/hr) Number of Machines per station Time (minutes)
Punching 15 4 4.0
Braking 12 4 5.0
Assembly 20 2 3.0
Finishing 50 1 1.2
New Line
Process Rate per Machine (parts/hr) Number of Machines per station Time (minutes)
Punching 120 1 0.50
Braking 120 1 0.50
Assembly 125 1 0.48
Finishing 125 1 0.48

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 15:30
Last week, linda's commission check was $84. if she earns a 12.5% commission on sales, what were her total sales?
Answers: 2
question
Business, 22.06.2019 19:30
The usa today reports that the average expenditure on valentine's day is $100.89. do male and female consumers differ in the amounts they spend? the average expenditure in a sample survey of 47 male consumers was $135.67, and the average expenditure in a sample survey of 38 female consumers was $68.64. based on past surveys, the standard deviation for male consumers is assumed to be $34, and the standard deviation for female consumers is assumed to be $17.
Answers: 1
question
Business, 22.06.2019 20:00
Lillypad toys is a manufacturer of educational toys for children. six months ago, the company's research and development division came up with an idea for a unique touchscreen device that can be used to introduce children to a number of foreign languages. three months ago, the company produced a working prototype, and last month the company successfully launched its new device on the commercial market. what should lillypad's managers prepare for next? a. increased competition from imitators b. a prolonged period of uncontested success c. a sharp decline in demand for the product d. a difficult struggle to move from invention to innovation
Answers: 2
question
Business, 23.06.2019 11:00
If you wanted to gain workplace experience and learn more about a company, what opportunity would be most ? a. job shadowing b. an informational interview c. an internship d. online research
Answers: 2
You know the right answer?
Positively Rivet Inc. is a small machine shop that produces sheet metal products. It had one line de...
Questions
Questions on the website: 13722367