On February 1, 2020, Nash's Contractors agreed to construct a building at a contract price of $5,700,000. Nash's estimated total construction costs would be $3,920,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows: 2020 2021 2022
Total costs incurred to date $1,470,000 $2,580,000 $4,550,000
Estimated costs to complete 2,450,000 1,720,000 -0-
Customer billings to date 2,100,000 3,920,000 5,500,000
Collections to date 1,900,000 3,400,000 5,400,000

Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and for completed-contract accounting, show the gross profit that should be recorded for 2020, 2021, and 2022.

2020 $ 2020 $
2021 $ 2021 $
2022 $ 2022 $

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 13:30
1. is the act of declaring a drivers license void and terminated when it is determined that the license was issued through error or fraud.
Answers: 2
question
Business, 22.06.2019 15:10
Popeye produces 20 cans of spinach in 8 hours. wimpy produces 15 hamburgers in 10 hours. if each hamburger trades for 1.5 cans of spinach, then: a.wimpy’s production and productivity are greater than popeye’s. b.popeye’s production is greater than wimpy’s, but his productivity is less. c.wimpy’s production is greater than popeye’s, but his productivity is less. d.popeye’s production and productivity are greater than wimpy’s.
Answers: 3
question
Business, 22.06.2019 20:30
Hank itzek manufactures and sells homemade wine, and he wants to develop a standard cost per gallon. the following are required for production of a 70-gallon batch. 2,700 ounces of grape concentrate at $0.04 per ounce 77 pounds of granulated sugar at $0.43 per pound 133 lemons at $0.79 each 350 yeast tablets at $0.24 each 350 nutrient tablets at $0.14 each 2,500 ounces of water at $0.001 per ounce hank estimates that 4% of the grape concentrate is wasted, 9% of the sugar is lost, and 32% of the lemons cannot be used. compute the standard cost of the ingredients for one gallon of wine. (round intermediate calculations and final answer to 2 decimal places, e.g.
Answers: 3
question
Business, 22.06.2019 22:20
With q7 assume the sweet company uses a plantwide predetermined overhead rate with machine-hours as the allocation base.and for q 10,11,13,and 14,assume that the company use department predetermined overhead rates with machine-hours as the allocation bade in both departements.7. assume that sweeten company used cost-plus pricing (and a markup percentage of 80% of total manufacturing cost) to establish selling prices for all of its jobs. what selling price would the company have established for jobs p and q? what are the selling prices for both jobs when stated on a per unit basis assuming 20 units were produced for job p and 30 units were produced for job q? (do not round intermediate calculations. round your final answers to nearest whole dollar.)total price for the job for job p -job q selling price per unit for job p q . how much manufacturing overhead was applied from the molding department to job p and how much was applied to job q? (do not round intermediate calculations.) job p job q manufacturing overhead applied for job p for job q . how much manufacturing overhead was applied from the fabrication department to job p and how much was applied to job q? (do not round intermediate calculations.)job p job q manufacturing overhead applied for job p for job q . if job q included 30 units, what was its unit product cost? (do not round intermediate calculations. round your final answer to nearest whole dollar.)14. assume that sweeten company used cost-plus pricing (and a markup percentage of 80% of total manufacturing cost) to establish selling prices for all of its jobs. what selling price would the company have established for jobs p and q? what are the selling prices for both jobs when stated on a per unit basis assuming 20 units were produced for job p and 30 units were produced for job q? (do not round intermediate calculations. round your final answer to nearest whole dollar.)total price for the job p for job q selling price per unit for job p for job q
Answers: 1
You know the right answer?
On February 1, 2020, Nash's Contractors agreed to construct a building at a contract price of $5,700...
Questions
question
Mathematics, 20.05.2021 02:50
question
Biology, 20.05.2021 02:50
question
Mathematics, 20.05.2021 02:50
question
Mathematics, 20.05.2021 02:50
Questions on the website: 13722361