Crane Company uses job order costing for its brand new line of sewing machines. The cost incurred for production during 2019 totaled $20000 of materials, $16000 of direct labor costs, and $13000 of manufacturing overhead applied. The company ships all goods as soon as they are completed which results in no finished goods inventory on hand at the end of any year. Beginning work in process totaled $22000, and the ending balance is $16000. During the year, the company completed 25 machines. How much is the cost per machine

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 10:00
Cynthia is a hospitality worker in the lodging industry who prefers to cater to small groups of people. she might want to open a
Answers: 3
question
Business, 22.06.2019 11:30
On average, someone with a bachelor's degree is estimated to earn times more than someone with a high school diploma. a)1.2 b)1.4 c)1.6 d)1.8
Answers: 1
question
Business, 22.06.2019 14:30
In our daily interactions we can find ourselves listening to other people solely for the purpose of finding weakness in their positions so that we can formulate a convincing response. select one: true false
Answers: 1
question
Business, 22.06.2019 15:00
Which of the following is least likely to a team solve problems together
Answers: 1
You know the right answer?
Crane Company uses job order costing for its brand new line of sewing machines. The cost incurred fo...