Using the shortest remaining time first scheduling algorithm, show the gantt chart for the scheduled processes and compute the average waiting time.
the time slice (quantum) values is 3.
process arrival time burst time
p1 0 8
p2 2 11
p3 3 5
p4 0 6
p5 7 15

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 21.06.2019 23:00
What is one of the main problems that can occur when implementing a large number of new systems within an organization?
Answers: 1
question
Computers and Technology, 22.06.2019 04:30
Eye injuries usually occur as a result of all of the following things, except: a) proper machine operation b) battery explosion c) falling or flying debris d) electric welding arc
Answers: 2
question
Computers and Technology, 22.06.2019 06:00
Write a program that uses a widgetviewer object to do the following: generate two random integers between 1 and 9 (inclusive). name one of them x, the other y. display them to the user using jlabel objects. create a jlabel object displaying the text "enter an operation number." create a jtextfield for the user's input. create a jbutton displaying the text "press here when you've entered your operation." use addandwait to add it to the widgetviewer object. when the user clicks the jbutton, evaluate operation in the following order to determine the one and only mathematical operation to perform on x and y. use a jlabel to display the result. if operation is between 1 and 10 inclusive, add x and y. if operation is evenly divisible by 4, subtract y from x. if operation is evenly divisible by 5, use integer division to divide y into x. if operation is an even number, use floating point division to divide y into x. if none of the other tests on operation apply, multiply x and y. note: operation can be negative or zero.
Answers: 2
question
Computers and Technology, 23.06.2019 07:00
You need a quick answer from a coworker. the most effective way to reach your coworker is through a. cloud server b. instant message c. teleconference d. telepresence
Answers: 1
You know the right answer?
Using the shortest remaining time first scheduling algorithm, show the gantt chart for the scheduled...
Questions
Questions on the website: 13722362