subject
Engineering, 17.12.2019 01:31 NotAPDB1441

From the niebel's methods, standards, and work design 13th editon textbook chapter #14 problem #1:

1.) the analyst in the dorben reference library decides to use the work sampling technique to establish standards. twenty employees are involved. the operations include cataloging, charging books out , returning books to their proper location, cleaning books, record keeping, packing books for shipment, and handling correspondence. a preliminary investigation resulted in the estimate that 30 percent of the group's time was spent in cataloging. how many work sampling observations would be made if it were desirable to be 95 percent confident that the observed data were within a tolerance of +/- 10 percent of the population data? describe how the random observations should be made. the following table illustrates some of the data gathered from 6 of the 20 employees. the number of volumes cataloged equals 14,612. from these data, determine standard, in hours per hundred, for cataloging. then design a control chart based on +/- 3 sigma limits for the daily observations. operators

item smith apple brown green baird thomas

total hours worked 78 80 80 65 72 75
total observations (all elements) 152 170 181 114 143 158
observations involving cataloging 50 55 48 29 40 45
average rating 90 95 105 85 90 100

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 18:20
Inadequate stores control is not an obstacle to effective work order system. (clo4) a)-true b)-false
Answers: 3
question
Engineering, 04.07.2019 18:20
Refrigerant-134a enters the compressor of a refrigerator as superheated vapor at 0.14 mpa and -10°c at a rate of 0.05 ka/s and leaves at 0.8 mpa and 50°c. the refrigerant is cooied in the condenser to 0.72 mpa and 26'c. it is then throttled to 0.15 mpa. sketch the t-s diagram for the system and evaluate: 6) the rate of heat removai from the refrigerated space (kw), it) the power input to the compressor (kw), ii) the isentropic efficiency of the compressor (%), and iv) the cop of the refrigerator.
Answers: 2
question
Engineering, 04.07.2019 19:20
Ashielded metal arc-welding operation is accomplished in a work cell by a fitter and a welder. the fitter takes 5.5 min to load components into the welding fixture at the beginning of the work cycle, and 1.5 min to unload the completed weldment at the end of the cycle. the total ength of the weld seams 1200 mm, and the travel speed used by the welder averages 300 mm/min. every 600 mm of seam length, the welding stick must be changed, which takes 0.8 min. while the fitter is working, the welder is idle (resting): and while the welder is working the fitter is idle. (a) determine the average arc-on time as a fraction of the work cycle time. (b) how much improvement in arc-on time would result if the welder used flux-cored arc welding (manually operated), given that the spool of weld wire must be changed every 10 weldments, and it takes the welder 5.0 min to accomplish the change? (c) what are the production rates for these two cases (weldments completed per hour)? attach your work and solutions.
Answers: 1
question
Engineering, 06.07.2019 03:10
Steel balls 12 mm in diameter are annealed by heating to 1150 k and then slowly cooled to 400 k in an air att 325 k and h -20 w/m2 k. assume the properties of the steel to be k- 40 w/m k,p 7800 kg/m3, and cp 600 j/kg k. a. determine whether lumped system method can be used to analyze this problem and if so why" b. determine the time required for the cooling process. c. determine the total amount of heat lost from each ball to the ambient air
Answers: 1
You know the right answer?
From the niebel's methods, standards, and work design 13th editon textbook chapter #14 problem #1: <...
Questions
question
Mathematics, 27.06.2019 13:00
question
History, 27.06.2019 13:00
question
Mathematics, 27.06.2019 13:00
Questions on the website: 13722362