You are in charge of estimating the runoff for generated over a 40-acre basin due to a 100-year 30-min design storm that produced 2.71 inches over 30 minutes, assuming uniform precipitation over the 30 minutes. The soils in the watershed are 33% clay, 59% silt and 8% sand. Prior to the storm, the soil had an effective saturation of 25% with an initial infiltration capacity of 17.8 cm/hr. From previous events, it was determined that the soil has a time constant k of 3.45 hr-1, and an ultimate infiltration capacity of 1.7 cm/hr. a. Derive an equation for time to ponding using the Horton model
b. Estimate the time to ponding (minutes) for the watershed basin using the Horton model and the Green-Ampt model. Discuss why these values are the same/different.
c. Use the Horton and Green-Ampt model to estimate the total infiltration (cm) during the storm
d. What is the runoff (acre-ft) using the Horton model and Green-Ampt model?

ansver
Answers: 3

Another question on Engineering

question
Engineering, 03.07.2019 19:30
When using the ohmmeter function of a digital multimeter, the leads are placed in what position relative to the component being tested? a. parallel b. control c. series d. line
Answers: 3
question
Engineering, 04.07.2019 18:10
Steel is coated with a thin layer of ceramic to protect against corrosion. what do you expect to happen to the coating when the temperature of the steel is increased significantly? explain.
Answers: 1
question
Engineering, 04.07.2019 18:10
Ifa component is made of two or more materials with different modulus of elasticity (e), it is called a composite member and we calculate the factor·n". mention the formula for calculating n". also, ifn> 1, explain what will happen to the 1. transformed.gi) ifn 1, what will happen to the material when transformed material when
Answers: 1
question
Engineering, 04.07.2019 18:10
Aturning operation is performed with following conditions: rake angle of 12°, a feed of 0.35 mm/rev, and a depth of cut of 1.1 mm. the work piece is aluminum alloy 6061 with t6 heat treatment (a16061-t6). the resultant chip thickness was measured to be 1.0 mm. estimate the cutting force, fc. use shear stress of 207 mpa and coefficient of friction on the tool face of 0.6.
Answers: 1
You know the right answer?
You are in charge of estimating the runoff for generated over a 40-acre basin due to a 100-year 30-m...
Questions
question
Mathematics, 24.08.2019 03:30
question
Mathematics, 24.08.2019 03:30
Questions on the website: 13722362